Project name |
TERMINAL II CAIRO INTERNATIONAL AIRPORT |
Customer |
LIMAK |
End User |
CAC |
Segment |
PMCS |
Country |
EGYPT |
Duration |
2014 - 2016 |
Scope :
Design,Supply,Engineering, configuration,programming and commissioning of SCADA & power Managmement System (PME) for Medium Voltage (MV) SWGR & Low Voltage (LV) SWGR inside the Airport.
Solution Description :
Two Control rooms each one have redundant servers & Two Workstations to Monitor & Control the following :
- Qty (2) LV SWGR Panel and Qty (3) MV SWGR Panel through QTy (1) DCONC Control panel in power plant building.
- Qty (13) LV SWGR Panel and Qty (1) MV SWGR Panel through QTy (1) DCONC Control panel in building C.
- Qty (26) LV SWGR Panel and Qty (2) MV SWGR Panel through QTy (2) DCONC Control panel in building B.
- Qty (10) LV SWGR Panel and Qty (1) MV SWGR Panel through QTy (1) DCONC Control panel in building A.
- Qty (600 ) Power Meter & protection relays Installed inside LV & MV Panels
- Integration with Generators, Transformers& UPSs exist in the System